CITY of RAPID CITY Agenda Item Summary |
|||
|
|||
Public Works Committee Meeting Date: 4/30/2013 |
City Council Meeting Date: 5/6/2013 |
||
Staff Contact: Stacey Titus |
Petitioner: |
||
Location: West of Sagewood Street |
|
||
Agenda Title: |
|||
Authorize Mayor and Finance Officer to Sign Amendment No. 2 to an Agreement between the City of Rapid City and Banner Associates Inc. for Professional Services for Northridge Water Storage Reservoir, Project No. W09-1792 / CIP No. 50754, in the amount of $66,792.00. |
|||
Summary: |
|||
The project has been delayed approximately 11 months due to problems associated with the prime contractor’s painting sub-contractor. The painting sub-contractor failed to comply with project drawings and specifications. The consultant had to duplicate services and expend additional effort as a result of these delays. In addition, the City of Rapid City requested additional start-up services associated with the Northridge Water Booster Station project. |
|||
Funding Source & Fiscal Impact (if applicable): |
|||
0602/0934 – Water Expansion |
|||
Recommendation: |
|||
Action: Approve Notes: |
|||
Options: |
|||
|
|||
Attachments & Links: |
|||
|
|||
|
|
|
|
|
|
|
|